Vials

Adequacy of Access and Collector Roads National Route N°12

  • Completion: June 2022
  • Location: San Nicolas Misiones (Argentina)
  • Client: DPV - DNV

With the need to order and provide greater safety to the entrance and exit to the town, to the Bus Terminal, and to the users of the RN Nº12 who wish to make a left turn and return maneuvers, it was decided to make an intersection in such a way that it orders the returns and collectors. 

It was proposed to induce a reduction in the speed of vehicles traveling on the road by means of traffic islands and chicanes made of thermoplastic paint, with reflective studs and signage support, which generate a single lane that makes a smooth "S" and causes a reduction in speed.

Other actions:

* The left turn from the main roadway was eliminated.
* An over-width was created with an access branch that allows deceleration and access to the right collector.
* A deceleration lane and an access branch were built leading to an additional lane parallel to the collector road.
* Markings with thermoplastic paint and reflective strips were made on the entrance to order the exit from Sarmiento Avenue and the entrance to it from NR Nº12.
* Pedestrian paths were painted near the terminal and at the main intersection.
* Necessary works such as repair and construction of curbs and gutters, speed bumps and storm drains, recovery of gauges and repaving to favor vehicular circulation and optimize drains in the roadway, lighting of intersections, horizontal and vertical signaling were also carried out.

1 km

in length

748 m3

of embankments

11.872 m2

asphalt

3.866 m3

excavation

Demolition of various works: 1.251,73 m2
Excavation for unclassified foundations: 402,62 m3
Construction of a 1.00m curb and gutter.: 27,00 m
Construction of curb and gutter: 228,23 m
Concrete h-17: 75,60 m3
Provision and placement of special steel for concrete adn 420: 1.32 tn
Spout diameter 0.80m: 80,00 m
Execution of base and granular sub-base: 110,45 m3
Execution of asphalt base: 4.777,20 m2
Execution of asphalt layer: 7.094,98 m2
Gauge reconstitution: 147.28 tn
Thermoplastic thermoplastic spray painting horizontal signage: 1.181,81 m2
Reflective studs: 222 u
Entepado: 147,40 m2
Excavation not classified as a deposit: 3.463,50 m3
Embankments with special compaction: 748,37 m3
Construction of a 0.50m curb and gutter.: 369,30 m
Construction of speed bumps: 112,12 m
Concrete h-21: 21,91 m3
Supply and installation of metal gratings for drains.: 3,50 m2
Pipe diameter 1.00m: 80,00 m
Execution of granular base with ballast: 1.490,11 m3
Execution of league irrigation: 9.238,94 m2
Surface potholes: 25,63 m2
Vertical signage: 83,44 m2
Horizontal marking with thermoplastic paint by extrusion: 261,85 m2
Lighting: 1 gl