Reconquista Water Treatment Plant

  • Completion: 2021
  • Location: Reconquista Santa Fe (Argentina)
  • Client: Ministry of Infrastructure and Transportation - Secretariat of Water - Santa Fe

The project will provide a drinking water flow of 108,000 m3 per day to cover the demand of 21 towns in northeastern Santa Fe. This plant is designed and projected to operate for at least 30 years and will have a remote management and fiber optic control system in a centralized network.

The following tasks were performed:

- Concrete water treatment plant and water treatment plant

- Ground movement and internal circulations

- Drinking water treatment train (pipes, valves, gates, fittings, etc.).

- Pumping station EBL and EBAP

- Casa Química Civil and Casa Química Equipamientos

- External site dewatering system

- Internal storm and sewage drainage system.

- Mud treatment and architectural works

- Electrical power and electromechanical equipment

- Calibration and commissioning

7.534m

in length

332.602 m3

of embankments

94,479 tn

asphalt

4.579 m3

concrete

Awesome Image
  • Technical data
  • More data
Length: 7.534,00 m
Asphalt 94,479.71 Tn
Reinforced concrete (miscellaneous): 2,771.30 m3
Paving (base and binder): 480,444.18 m2
Pluvial drainage (pipes): 1,071.59 m
Crosswalks, high level and low level: 3 u
Relocation of interferences for 13.2KV electrical line duct: 866.02 m
Relocation of interferences, provision and pre-assembled overhead laying of 13.2KV or 33KV medium voltage: 1,908.48 m
TERRAPLENES: 332.602,57 m3
ASPHALT: 480,444.18 m2
REINFORCED CONCRETE (VIADUCT): 1,808.58 m3
NEW JERSEY TYPE RAILINGS: 7.534,00 m
VIADUCTS (LONG. 32M): 2 u
LIGHTING - SUPPLY AND PLACEMENT OF 90 MM. PIPES: 4,841.06 M3 4.841,06 m
RELOCATION OF INTERFERENCES-PROVISION AND UNDERGROUND CONSTRUCTION OF MEDIUM VOLTAGE 33 KV: 557.27 m