Repair of Surface and Deep Potholes and Sealing of Joints

  • Completion: September 2023
  • Location: Palo Santo Formosa (Argentina)
  • Client: Dirección Provincial de Vialidad

The work refers to the reconstruction of the road on Provincial Route No. 3, between the Pighó Chico estuary and the junction with RN 86 and also referring to RP 23, between the town of Baños to the town of Palo Santo.

2 Km

in length

1.183 M3

of embankments

4.714 tons

asphalt

37,715 M2

asphalt used

Demolition and extraction of structural layers : 13,980.95 m3
Construction of 4% lime soil e=0.20m, a=8.00m : 4072.24 m3
League irrigation : 39,502.22 m2
Construction of ca folder e=0.05m, a=7.30 : 18,580.22 m2
Subgrade sanitation e=0.20m : 4178.24 m3
Construction of subbase e°g° e=0.20m, a=7.80m : 2978.38 m3
Base construction ca e=0.07m, a=7.50m : 19,134.85 m2
Embankment with special compaction : 1,183.22 m3